Work is underway near the 133rd kilometer of the highway. First, specialists are laying metal pipes that will serve as the foundation for temporary traffic. Heavy construction equipment has been brought to the site for this purpose.
Simultaneously, drilling of boreholes has begun. These are needed for cast-in-place piles, which will allow the restoration of the bridge's intermediate pier. Additionally, the dismantling of concrete slabs on one of the spans has been completed, and the disassembly of reinforced concrete slabs on the second span has started. The process involves a 100-ton mobile crane, two excavators, and dump trucks.
You can follow the progress of the restoration work on the official websites of GKU "Dagestanavtodor" and the Ministry of Transport and Road Industry of the Republic of Dagestan.