Engineers from the Stavropolskenergo branch have implemented a new 10 kV line that covers the settlements of Peskovsky and Tambukan, as well as the villages of Yutsa, Dzhutsa, and Etoka. Previously, these areas were powered by a radial scheme from a 35 kV substation, making them vulnerable to any accidents. Now, in the event of a failure on the main line, specialists can quickly switch consumers to an alternative power source.
The length of the new energy facility is almost three kilometers. It is constructed in a cable-overhead design and complements a reconstructed section of the existing network. Energy workers replaced old poles and dilapidated wires with self-supporting insulated cables (SIP). This design is characterized by high strength and safety, as well as better resistance to mechanical loads. Special attention was paid to the installation of a domestic recloser. This intelligent automatic circuit breaker with a relay protection system automatically identifies the location of the fault and disconnects the emergency section, minimizing the impact on other consumers.
As Igor Demchak, the branch director, noted, the location is characterized by complex meteorological conditions. In winter, strong winds, ice, and snowfalls regularly occur here, creating additional load on poles and wires. The implementation of modern equipment and a reserve circuit allows for a significant reduction in the time required to restore power and protects infrastructure from the region's natural whims.