Red Bridge Restoration in Dagestan Postponed to November

The restoration of the Red Bridge spans in the Gergebil District will not be completed before November 28 due to the repeated washing out of structures during water releases from the hydropower plant.

Red Bridge Restoration in Dagestan Postponed to November

The collapse of the metal spans occurred on October 2 following a sharp rise in water levels. The cause lies in the operation of the Gotsatlinskaya Hydropower Plant: the evening release increased the flow rate from 134 to 298 cubic meters per second. The powerful current washed out the embankment, shifted the temporary supports, and damaged the structures that had been lifted onto them prior to the dismantling of the damaged central support. Acting Minister of Transport and Road Infrastructure of Dagestan Dzhambulat Gadjiev reported that specialists are continuing to assess the condition of the beams and repair the cross-bracing. The current work schedule has been adjusted to account for these circumstances.

Initial plans to complete the emergency restoration work by the end of October were thwarted. The new deadline for project completion is set for November 28. This timeline is valid provided that additional inspections do not reveal hidden deformations in the main load-bearing elements. The contracting organization, Sibregionstroy, has already begun restoring the access road and dismantling the remaining slabs of the superstructure. The department emphasizes that the company is working without commercial profit, receiving only compensation for incurred expenses as instructed by the republic's leadership.

The lack of coordination between the construction teams and the energy sector has become the key reason for the delays. Previously, on September 25, the parties had reached an agreement on preliminary coordination of release volumes with RusHydro. However, on October 7, an uncontrolled release again washed out the embankment. The minister insists on introducing strict liability for uncoordinated actions, as they pose a direct threat to the lives of the builders and negate the results of their labor. Temporary detours through culverts were rejected due to the risk of structural collapse during floods, so priority is given to the safety of drivers and passengers using alternative routes to connect with the mountainous regions.